ROAD WORK

June 26, 2020

Wildstone will be working on the green spaces, getting ready for top soil. They will also put in the vacant lot water sewer post on Kathleen St. and in the alley.

The traffic will not be impacted by this work.

 

 

ROADWORK
June 25, 2020

Wildstone will be painting and / or replacing the markers for vacant lots on Kathleen St. and Auriol St. and also working in the RCMP alley locating where the bleeder was and backfill and pack.
Traffic will not be impacted by this work

 

ROADWORK

June 24 2020

we will be working in the RCMP alley on the 6x6 retaining wall, also the markers; for vacant lot on Kathleen St. And Auriol St.

The traffic will not be impacted by this work. 

 
ROADWORK
June 19, 2020
Wildstone will be removing culvert forms from multiple locations. This will not impact traffic or driveways. They will also be working in front of the Parks building and possibly completing some ditch work on the corner of Kathleen St. and Lucania St.
There will be no work going on over the weekend!
ROADWORK
June 18, 2020
Wildstone will be continuing work in the RCMP alley as well as behind Cozy Corner in the lane way installing bollards.
They will also continue working on culvert headwall installation. Around 11:30 a.m. -12:00 p.m. there will be a concrete truck moving around to multiple locations.
Wildstone will always try to keep one lane of traffic open, but sometimes this is not possible. If this is the case, it will be for a very short duration
 
ROADWORK
June 17, 2020
Wildstone will be working in RCMP alley installing hydrant bollards and also will be in the same area working on culvert ends and should not disrupt traffic or driveways. We will be continuing driveway grading on Auriol , Mackintosh , Lucania.
 
ROADWORK
June 16, 2020
Today, Wildstone will be working on Lucania St. from Kathleen St. to Auriol St. They will try to maintain single-lane traffic, but encourage community members to make a detour.
They will also be completing some ditch work at the west end of Kathleen St. after finishing work on Lucania St.
They will have crews working around Lowell St., Macintosh St. and Kluane St. doing driveway grading and ditch work.
 
ROADWORK
June 15, 2020
Today Wildstone will be working on multiple streets, painting fire hydrant bollards and grading around them. There will be a crew going around placing gravel and leveling driveways .
They will also be replacing the wood retaining wall beside the RCMP office.

ROADWORK
June 13 - 14, 2020
For this upcoming weekend, Wildstone will be removing existing asphalt on Lucania St. from Auriol St. to Kathleen St. That section of road will be closed! Vehicles can detour via Kathleen St. to Logan St. and Auriol St.

The road will be open at the end of the day on Saturday. We will also have workers working in the ditches and driveways removing wood forms. This should not impact any residences.

Time permitting, Wildstone might be working on the walking path that is parallel to Kathleen St. at Logan St. on southside.

ROADWORK

June 12, 2020
Today Wildstone will be continuing culvert head wall work on Lucania St. and Kathleen St. and installing fire hydrant bollards in the same area.
There will be a cement truck in the area around noon.
 
ROADWORK
June 11, 2020
On June 11, 2020, Wildstone will be working around the fire hydrants excavating and installing bollards starting on the corner of Lucania St. and Lowell St.
Wildstone will also continue installing forms around culvert ends. There may be some single-lane traffic, otherwise there should be no traffic disruption.
 
ROADWORK
June 10, 2020
Wildstone will continue working on Lucania St. back-filling the service line repaired yesterday.
Work will also continue on prepping the culvert ends on driveways.
 
ROADWORK
June 9, 2020
Wildstone will be doing excavation work on Lucania St. at Mackintosh St. There will be one lane of traffic on Lucania St. as long as it is safe to do so. There is a possibility that they will need to close the road at that location until 5:00 p.m.
There will also be a crew going around installing forms around culvert ends starting at Lowell St. working their way South. This work should not cause any traffic disruption.

By-Election

Contact Information

The Village of Haines Junction
Box 5339
Haines Junction, Yukon
Canada Y0B 1L0
phone: (867)634-7100
fax: (867)634-2008
email:admin@hainesjunction.ca

Colouring Contest Artists